Kawartha Lakes has been courting Queen’s Park over a four-lane Highway 35 south of Lindsay for years. The province has made plans. It has even bought land. The city is still waiting for a date.
At the corner of Highways 35 and 7A, there is a parcel of land the province has owned for 15 years. Until 2011, it was my aunt and uncle’s house. The place of many big family Christmas dinners. The Ontario Ministry of Transportation acquired it that year after registering an order-in-council, telling the family it needed the land to widen Highway 35.
The highway beside it is still two lanes.
In the years since, Kawartha Lakes has agreed to grow, and has grown, much as Queen’s Park asked. The province has drawn a route for a wider highway and bought land to build it. What it has not done is say when. A courtship without commitment.
A plan on paper, not pavement
A 2007 provincial planning study looked at four-laning Highway 35 south of Lindsay. This fall, the ministry told the Advocate it has completed a preliminary design report and a transportation environmental study report and has designated a preferred alignment for a four-lane highway from Enterprise Hill to Highway 7 at Lindsay.
The rest of its response was the ministry’s familiar line: a province-wide spending figure and a reminder that large projects advance in phases.

The premier’s word
In December 2018, then-mayor Andy Letham got a 45-minute, one-on-one meeting with Premier Doug Ford at Queen’s Park. High on his list was widening Highway 35 south of Lindsay.
Letham told Kawartha Lakes This Week that Ford saw the case for it, with the Highway 407 extension to Highway 35/115 due to open and said he would “look at the schedule and look at moving it up.”
The 407 extension opened Dec. 9, 2019. The widening has not moved up.
The city’s end of the bargain
At the city’s request, the Ford government issued minister’s zoning orders for new neighbourhoods east and south of Lindsay and at Highway 35 and Colborne Street. In 2023, the city said those lands accounted for about 10,000 of 17,000 homes in its planning pipeline.
Council signed the province’s housing pledge, accepting a target of 6,500 new homes by 2031 — more than the City of Peterborough’s 4,700. Kawartha Lakes reached 90 per cent of its 2023 target and 83 per cent in 2024, enough both years to earn provincial Building Faster Fund money. Its growth strategy plans for 130,000 residents by 2051.
The city also carries roads the province handed off. In 1997 and 1998, Ontario downloaded all or parts of provincial Highways 36, 46, 48, 121, 503, 505 and 649 to Victoria County. Kawartha Lakes taxpayers now maintain them, and road infrastructure was a concern voiced throughout this fall’s municipal election.
That includes the downloaded Lindsay Street bridge in Fenelon Falls, on former Highway 121 and the town’s only river crossing. Inspectors have flagged its deterioration, and replacing it will fall to the city. Highway 35 is still Ontario’s.
The road today
At the Highway 115/35 split, Highway 35 narrows from four lanes to two. It runs north past the CPKC rail line at Pontypool, a corridor raised in public consultations on Alto’s planned high-speed rail line to Peterborough. It crosses the Oak Ridges Moraine, our part of the Greenbelt, at Ballyduff, then rolls through the hills of Manvers, where loaded trucks slow on the climbs, before flattening out in Ops.
Ministry figures show average daily traffic on the section beginning at Enterprise Hill rose from 7,150 vehicles in 2019 to 8,400 in 2024, about 17 per cent.
Jason Hore, who owns St. Dave’s Diner on Highway 35, told the Advocate he has heard about four-laning since he bought the business. “Here we are eight years later,” he said.
His diner sits on a stretch just south of Highway 7 that is already five lanes wide, and from there he doesn’t think the highway necessarily needs more lanes. His concern is safety. He has seen many collisions across the road from his restaurant and says guardrails “would be a huge improvement.”

The province’s case
Ontario has a $5.4-billion highway and bridge budget for 2026-27 and no shortage of competing demands. Rising daily averages alone don’t prove the corridor needs four lanes, and a phased approach is reasonable.
What is missing is any public sign of which phase comes next south of Lindsay, and when. Think about that the next time you’re behind a loaded truck on a Manvers hill.
What to ask
Mayor Charlie McDonald and council face a long list of provincial asks. At this summer’s Association of Municipalities of Ontario conference, the city’s delegation raised policing costs, paramedic services, rural firefighting, public health funding and a share of the HST rebate for roads and bridges. AMO has also asked the province for a social and economic prosperity review, in effect a new deal on who pays for what.
On Highway 35, McDonald could start by asking Ford what came of the 2018 conversation with Letham, then follow up on Elmslie’s request to the province for GO bus service to Lindsay, which he pressed for more than two years.
Council and Laurie Scott, MPP for Haliburton-Kawartha Lakes-Brock, could press for an updated corridor forecast, a public timetable with the conditions that would trigger construction, and interim safety work such as turn lanes, passing lanes and guardrails where collision records support it.
Kawartha Lakes has taken the growth the province asked for. The province has a route, the land and a premier who said he would look at moving it up. The people who drive Highway 35 deserve to know when that plan becomes pavement.
Scott’s office did not respond to a request for comment by press time.
— with files from Robyn Best.